UEET 101: Introduction to Engineering

Spring 2007

Group 6 Reverse Engineering Project


Team Lead:
Timothy Pearson kb9vqf@pearsoncomputing.net

Members:
Justin Pappachan
Purav Patel
Tim Sagel
Eric Pratt
Photo gallery
      Forum

   First Draft
 Second Draft
   Final Draft
Current Project Status as of 4/27/07:
Final draft complete.

Weekly Status Reports:
Week of 1/28/07:
 
Entire team met for the first time; team lead was chosen.
Website was started.
 
Week of 2/04/07:
 
 
 
Team meeting.
Household blender was chosen as dissection project.
Blender was dissected; pictures were taken; and reassembled blender works fine.
 
Week of 2/11/07:
 
Class cancelled due to snow.
Initial draft in progress.
Week of 2/18/07:
Initial draft complete. Viewable here.
Week of 2/25/07:
Second draft in progress.
Week of 3/04/07:
Second draft in progress.
Week of 3/11/07:
Spring Break!
Week of 3/18/07:
Second draft complete. Viewable here.
Week of 3/25/07:
Final draft in progress.
Team met after class to discuss deadlines.
The due date for final reports is April 13, 2007.
Week of 4/1/07:
Final draft in progress.
Week of 4/8/07:
Final draft in progress.
Week of 4/15/07:
Final draft in progress.
Week of 4/22/07:
Team met after class to discuss removal of non-contributing members.
Final draft complete. Viewable here.

Research Assignments: Date Assigned: Due Date: Date Completed:
Market Analysis:
Purav Patel
Thu 2/8/2007
Wed 3/7/2007
Sat 3/24/07
 
Cost Analysis:
Purav Patel
Thu 2/8/2007
Wed 3/7/2007
Sat 3/24/07
 
Environmental Impact Analysis:
REASSIGNED

Wed 2/14/2007
Tue 3/20/2007
Tue 3/20/2007
Draft:
Tue 3/20/2007

 
Ethical issues:
REASSIGNED

Wed 2/14/2007
Tue 3/20/2007
Tue 3/20/2007
Draft:
Tue 3/20/2007

 
Safety issues:
REASSIGNED

Mon 2/12/2007
Tue 3/20/2007
Tue 3/20/2007
Draft:
Tue 3/20/2007

 
Electrical Engineering Analysis:
Timothy Pearson
Thu 2/8/2007
Wed 3/7/2007
Draft:
Thu 2/22/2007

 
Mechanical Engineering Analysis:
Timothy Pearson
Thu 2/8/2007
Wed 3/7/2007
Draft:
Thu 2/22/2007

 
Reliability Analysis:
Timothy Pearson
Thu 2/8/2007
Wed 3/7/2007
Draft:
Wed 3/7/2007

 
Industrial Engineering Analysis:
Timothy Pearson
Wed 2/14/2007
Wed 3/7/2007
Draft:
Thu 2/22/2007